Since 2018 Revision Zero has been working on the Carrapateena Underground Mine. In 2019 the works were completed. Revision Zero on the back of the work completed were awarded the Block Cave Expansion works. In 2021, one of the smaller packages were also award to Revision Zero, the Carrapateena Refrigeration Plant.
One of the biggest mining projects in South Australia in the last decade, Carrapateena Province is in the highly prospective Gawler Craton in South Australia. It’s already set to become a multi-generational, low-cost mining province.
Revision Zero completed this project, which included 3D modeling services as well as the preparation of drawings for structural steel for approximately 95 tons along with approximately 276 linear meters of handrail and total of 402 sq.m of Grating.
For this project, Scope of Work Consists of the following:
- Condenser Tower Support Structure 1 & 2
- Compressor Pipe Support & Grating
- Valve Access Platform & Pipe Bridge
- Chilled Water Pump Area (Pipe Support)
- Pump Station (Piping Steel Supports)
- Bollards and Stands